Castlemaine Tower

Cladding Removal

Background

Lancebox Ltd carried out the cladding removal to Castlemaine Tower, for Durkan.

Scope of works

  • Removal of combustible curtain walling panels to the entire 24 storey residential tower block, approx. 9500m²

  • Lancbox and Durkan guaranteed that works were completed on time and to a professional standard with minimal disruption to existing tenants, that remained in situ throughout the removal works.

What started out to be a relatively complex project, the bilateral and regular contact and communications with your project team onsite and office based, ensured that the task was not only completed to plan but ahead of schedule as well. I would have no hesitation at all in recommending Lancebox Ltd.
— Dan Ryder | Senior Project Manager, Durkan